- my recent pitch and my confusion
- client doesn’t have an idea of what they want
- like i need to introduce the current status quo to them
- their aesthetic makes me …= =b
- due to lack of understanding, he’s modifying the scope of the project a lot
- fragmented communication
- actual client (the dj girl) - shawn (the middle man, POC for us) - henry - me
- ask gpt - “make this email less passive aggressive”
- you tell me are you happy with the aesthetics? what do you speciifcally like about it? (the lighting? the moment of xxx? maybe they don’t like the whole thing)
- work with midjourney (client aesthetic + my aesthetic) find a middle way
- show them “i was thinking more like this” + listen to their feedback on it
- asking them to be specific
- scope - align my team, timeframe
- pitch - time spent on the pitch
- fast turn around, “1 month” keep track of me
- we’d love to get this started, when can we go to conrtact and NDAs? if we can’t move on, we have other clients
- 1k asset
- i have the portfolio they like, otherwise they wouldn’t talk to me at the first place
- 500 client will NEVER become 5000 client - it will never happen
- mo-cap included: 50+ 75-100/hr
- exposure: am i having my name on it? mentioned? or just shawn’s agency? what am i getting out?
- communication scope up - 10 hours of no direct communication w the client
- actual scope breakdown
- shoot day 8 hr, clean up 8 hr, look at finals - split to 2 ppl (10% add up on the hours)
- mocap - 1 ppl? 10 ppl?
- be specific on the contract
- what’s the line item? it’s easier for them to sign if we have line item
- out of scope section: if you need these xx day rate will apply
- and don’t do hourly
- if already lowballed - this is what you getting with this price, these are the items you didn’t get
- client is lowballing me obviously and how can i get around with that?
- whats the best time to talk about budget and timeline
- if it’s beyond this date - you need to pay me day rate (if you didn’t give me feedback on time)
- lock in iteration - above this charge more
- we will deliver on xx days, you have xx time range to provide feedback, you can’t give feedback after xx date, if you don’t give feedback 2 days after receiving, I will not be able to work on time.
- beginning: send things daily; middle - specific range of feedback period and working period.
- lets do meetings when all 3 of us are here?
- pre-veting dates, i need to hear from the actual client..